Back

Retainage

Updated
August 18, 2026
Link copied!

What Is Retainage?

Retainage is a percentage of each payment on a construction contract that the owner or general contractor withholds until the work is satisfactorily completed. Rather than paying a contractor or subcontractor the full amount of each invoice as work progresses, a portion is held back as security that the job will actually be finished to the required standard.

How Retainage Works

  1. A retainage percentage is set in the contract.
    Commonly 5% to 10%, agreed before work begins.
  2. Each progress payment is reduced by that percentage.
    The contractor invoices for work completed, and the owner pays the invoiced amount minus retainage.
  3. Retainage accumulates over the project.
    Building up as a held balance across every payment application submitted.
  4. Retainage is released at agreed milestones.
    Commonly at substantial completion, final completion, or a defined period after the punch list is cleared.

EXAMPLE

A subcontractor submits a pay application for $80,000 of completed work on a contract with 10% retainage.
Payment due = $80,000 × (1 − 0.10) = $72,000.
The remaining $8,000 accumulates as retainage, to be paid out later once the retainage release conditions are met.

Why Retainage Exists

Retainage gives the owner or general contractor leverage to ensure a contractor completes the work correctly, including fixing defects and completing punch list items, rather than walking away once the bulk of the payment has been collected. It functions as a form of security held throughout the project rather than a separate bond or deposit.

From the contractor's side, retainage represents real cash tied up in a project for months, sometimes the entire project duration, which is why it is a significant working capital consideration for subcontractors managing multiple jobs simultaneously.

Typical Retainage Rates and When They Reduce

5% and 10% are the most common rates, though the specific percentage is a matter of contract negotiation and varies by project type, project size, and regional practice. Some contracts reduce the retainage rate partway through a project, for example dropping from 10% to 5% once the project reaches 50% completion, to help contractor cash flow on longer jobs without eliminating the owner's security entirely.

Many states have retainage laws that cap the maximum percentage that can be withheld, particularly on public projects, and set requirements for when retainage must be released. These laws vary meaningfully by state, so the applicable rate and release timeline depend on the project's specific jurisdiction and whether it is public or private work.

Retainage Payable vs. Retainage Receivable

  • Retainage payable:
    From the paying party's perspective, a liability representing retainage withheld from a contractor or subcontractor that will eventually be owed to them.
  • Retainage receivable:
    From the contractor's perspective, an asset representing retainage that has been withheld from them but is expected to be collected once released.

Both are typically tracked separately from standard accounts payable and accounts receivable, since the timing of when retainage actually becomes due is governed by project milestones rather than standard invoice payment terms.

Retainage and Accounts Payable

For a general contractor managing many subcontractors, tracking retainage accurately means knowing, for every subcontractor and every pay application, how much has been withheld to date and under what conditions it becomes due. This is a different tracking requirement than standard AP, where an invoice is simply open or paid; retainage sits in a third state, withheld but not yet due, for an extended period.

Getting this wrong in either direction causes real problems: releasing retainage before completion conditions are actually met removes the leverage it exists to provide, while failing to release it once conditions are met is a common source of subcontractor disputes and, in some states, exposes the paying party to statutory penalties for late retainage release.

Frequently Asked Questions About Retainage

1. What is retainage?

Retainage is a percentage of each construction payment, commonly 5% to 10%, that the owner or general contractor withholds until the work is satisfactorily completed. It gives the paying party leverage to ensure the contractor finishes the job, including any defect corrections.

2. How does retainage work?

A retainage percentage is set in the contract, each progress payment is reduced by that percentage, and the withheld amounts accumulate over the project. Retainage is released at agreed milestones, typically substantial or final completion.

3. What is a typical retainage percentage?

5% and 10% are the most common rates in construction contracts, though the exact percentage varies by project type, size, and region, and some contracts reduce the rate partway through a project to help contractor cash flow.

4. What is the difference between retainage payable and retainage receivable?

Retainage payable is a liability from the paying party's perspective, representing amounts withheld that will eventually be owed. Retainage receivable is an asset from the contractor's perspective, representing amounts withheld from them that are expected to be collected once released.

5. When is retainage released?

Typically at substantial completion, final completion, or a defined period after outstanding punch list items are resolved, as specified in the contract. Many states also have laws governing maximum retainage rates and release timing, particularly on public projects.

6. How is retainage different from a regular unpaid invoice?

A standard invoice is either open or paid on normal terms. Retainage sits withheld but not yet due for an extended period tied to project milestones rather than standard payment terms, which requires tracking separately from ordinary accounts payable and receivable.

Track retainage without a separate spreadsheet.
LayerNext applies your retainage rules automatically on every construction invoice, so what is withheld and what is due stays accurate as each pay application posts.
Talk to Sales
No items found.
No items found.